A commercial production schedule template from bid to air date.

Every milestone on a typical commercial, in order, with typical durations and who owns each one. Use it as a checklist, copy it into a spreadsheet, or build it in Workback and save it as your own template.

This template follows a single national :30 with a :15 cutdown, produced by a production company for an agency and its client. Durations are in working days, so weekends and holidays come on top. Build it backward from the air date: start at the bottom of the table and work up.

The production schedule template

PhaseMilestoneTypical durationOwner
CreativeScript development5–10 daysAgency
CreativeScript approval1–3 daysClient
CreativeBoard-o-matic or animatic to client1 dayAgency
BidBrief production companies1 dayAgency
BidDirector treatments and bids4–6 daysProduction
BidBid review and award2–3 daysAgency
BidContracts and estimate approval1–3 daysClient
Pre-productionPrep begins10–15 daysProduction
Pre-productionCasting and location specs due1 dayProduction
Pre-productionCasting sessions and callbacks3–5 daysProduction
Pre-productionLocation scout2–5 daysProduction
Pre-productionCasting selects and locations to client1 dayAgency
Pre-productionTalent and location approval1–2 daysClient
Pre-productionTalent ICR1 dayAgency
Pre-productionInternal PPM1 dayAgency
Pre-productionPPM1 day, 4–7 days before the shootProduction
Pre-productionWardrobe fitting, tech scout, call sheet1–2 daysProduction
ShootShoot window1–3 daysProduction
EditorialLoad footage1 dayProduction
EditorialEditor's cut (unsupervised)3–4 daysProduction
EditorialDirector's and agency cut (supervised)4–5 daysProduction
EditorialCuts to ECD1 dayAgency
ReviewRC1 to legal and agency ICR1–2 daysAgency
ReviewRC1 to client, client notes2–3 daysClient
ReviewRevisions1–2 daysProduction
ReviewRC2 to client, legal feedback due2–3 daysClient
ReviewPicture lock1 dayProduction
FinishingOnline and conform1–2 daysProduction
FinishingColor session1–2 daysProduction
FinishingVFX and cleanup2–4 daysProduction
FinishingRecord VO, sound design, mix1–2 daysProduction
FinishingFinal masters ICR1 dayAgency
DeliveryMaster approval1 dayClient
DeliveryVersioning, captions, slates, QC1–2 daysProduction
DeliveryTraffic and ship1 day, before the station deadlineAgency
DeliveryAir dateFixedClient

Some milestones overlap. Casting and locations run inside prep, and finishing steps run in parallel once picture locks. Add them together and the runway from award to air is about six to eight weeks. To check your own dates, put your air date into the production schedule calculator.

Adapting it for :30, :15, and social

A single :30

Use the table as written. If the client is new or the creative is complex, plan for an RC3 and add three working days to review.

A :30 with a :15 cutdown

Cut the :15 from the :30 once the :30 is close to lock. Add one or two days of editorial and send both cuts in the same review round so the client gives notes once. The :15 needs its own pass through color, the mix, and legal, and its own master approval and traffic.

A social package

Social deliverables add aspect-ratio versions (9:16, 1:1, 4:5), on-screen copy, captions, and platform specs. Plan the social cuts as their own editorial block after the :30 locks, give them a review round, and add a posting schedule with a date per platform. If you shoot dedicated social content, add it to the shoot window as its own item so it doesn't get squeezed.

A multi-spot campaign

Add a Deliverable field and tag every milestone with the spot it belongs to. Then color or filter the calendar by deliverable to see each spot's path through post.

A :30, :15, and social package on one Workback calendar. Switch to List or Timeline to check every date.

Building it in Workback

  1. Create a project and add your parties (Agency, Client, Production) and stages.
  2. Place the air date first and lock it, so no later reschedule moves it.
  3. Work up the table. Drag across days on the calendar to create each event, or type them into the List view.
  4. Mark internal items like the internal PPM and bid review, so they stay off the client's link and exports.
  5. Assign people to the milestones they own, and check the Master Calendar for conflicts with other jobs.
  6. Share and save. Send the client a share link, save a named version, then save the project as a workspace template for the next job.

When the shoot moves, push and pull moves every later milestone in working days, skipping weekends and holidays. Locked dates stay put.

Building it with the AI connector

If you use Claude or ChatGPT, connect it to Workback and choose the "Build a schedule from a deadline" prompt. Give it the air date and the deliverables. It plans the milestones back from that date in business days, skipping weekends and holidays. Already have a schedule in a PDF or spreadsheet? Hand it over and it imports the events. See how the AI connector works.

For the reasoning behind the method, read how to build a production schedule and the production calendar guide. For the back half of the job in more detail, use the post-production schedule template.

Build this schedule in Workback. Start a free 30-day trial, no credit card required.

Common questions.

Six to eight weeks from award to air for a single national :30 with a cutdown. Eight weeks is comfortable, six is tight, and four means fewer review rounds and finishing that overlaps with the edit. Add the bid and creative development before award.

The agency producer usually owns the master schedule from brief to air date and shares it with the client. The production company's line producer owns prep and the shoot, and the post producer owns editorial through delivery. One shared calendar, with a party on every milestone, keeps all three in step.

A :15 cut from the same shoot adds a day or two of editorial and its own review and finishing passes. A social package adds aspect-ratio versions, platform specs, and often a separate posting schedule. See the section on adapting the template above for the details.

Yes, through the AI connector. Connect Claude or ChatGPT and use the "Build a schedule from a deadline" prompt with your air date. It plans the milestones back from that date in business days, skipping weekends and holidays.

Yes. Copy the table into a spreadsheet, or rebuild it in Workback during the free 30-day trial and save it as your own workspace template.