A post-production schedule template from ingest to delivery.
Every step from the last shoot day to the final deliverable, with the days each one needs and who usually owns it. Built for commercials and branded content, and easy to stretch for longer form.
This template follows a :30 with a :15 cutdown through a post house or in-house editorial team. Durations are in working days. Day 1 is the first day after the shoot wraps. Many steps in finishing run in parallel once picture locks, so the total runway is shorter than the sum of the rows.
The post-production schedule template
| Step | What happens | Typical duration | Owner |
|---|---|---|---|
| Ingest and sync | Footage backed up, transcoded, synced to sound, organized for the editor | 1–2 days | Assistant editor |
| Assembly | Editor builds a first assembly of the selects | 2–4 days | Editor |
| Director's cut | Director shapes the cut with the editor | 2–3 days | Editor, director |
| Offline and agency cut | Agency creative team works through the cut | 3–5 days | Editor, agency |
| Review round 1 | Cut to agency, then RC1 to client and legal, notes back | 2–3 days | Agency, client |
| Revisions | Editor works the notes | 1–2 days | Editor |
| Review round 2 | RC2 to client, final notes, legal feedback | 2–3 days | Client |
| Picture lock | The edit is approved, timing is final | 1 day | Post supervisor |
| Online and conform | Offline edit rebuilt with full-resolution media | 1–2 days | Online editor |
| Color | Color session, supervised by the director or DP | 1–2 days | Colorist |
| VFX and cleanup | Compositing, cleanup, graphics, supers | 2–5 days, runs in parallel | VFX artist |
| Sound and mix | VO record, sound design, music, final mix | 1–2 days | Mixer |
| Final review | Final masters ICR and client approval | 1–2 days | Agency, client |
| Deliverables | Versions, cutdowns, aspect ratios, captions, slates | 1–3 days | Post supervisor |
| QC and delivery | Technical QC against specs, delivery to traffic or platforms | 1 day | Post supervisor |
Add it up and a single :30 with a cutdown runs about three to five weeks from wrap to delivery. Ask for delivery specs from the network or platform early. A missing spec found during QC can cost a day you don't have.
A post schedule on a Workback calendar, color-coded by stage, with each step assigned to the editor, assistant editor, or colorist.
How to plan post
Work back from delivery
Start from the delivery or traffic deadline and place each step behind it. Picture lock is the date that matters most. Protect it, and put any buffer in editorial, where the editor can absorb a day.
Book every review round as a round trip
A review round is a send date, review time, a notes deadline, and revision days. Clients and legal often need more time than the schedule gives them. Put each step on the calendar with the client as the owner, so the dependency is visible to everyone.
Run finishing in parallel
Once picture locks, online, color, VFX, and sound can overlap. The Timeline view is the easiest way to plan the overlap and see which steps share a person.
Watch the people as well as the dates
The same editor or colorist is often booked on several jobs. Assign post steps to people, then check the Master Calendar for conflicts and time off before you commit to a lock date. See resourcing.
Building it in Workback
- Create a project and add stages for Editorial, Review, Finishing, and Delivery.
- Place and lock the delivery date, then work back through the table.
- Assign each step to the editor, colorist, mixer, or a tracked freelancer.
- Add tasks for the work behind each milestone, like pulling music options or sending the VFX shot list. Track them on the task board.
- Share a link with the agency and client that hides internal tasks and notes.
- Save it as a template so every post job starts with your steps and durations.
When the shoot slips or a review round runs long, push and pull moves every later step in working days, skipping weekends and holidays. To bring an existing post schedule across, connect Claude or ChatGPT through the AI connector and hand it the PDF or spreadsheet.
More for post teams: Workback for post-production, the commercial production schedule template for the full job, and the production calendar guide.
Common questions.
About three to five weeks from the last shoot day to delivery for a single :30 with a cutdown: one to two weeks of editorial, a week or more of review rounds, about a week of finishing, and a few days for deliverables and QC. Heavy VFX or a long deliverables list adds time.
Picture lock is the point where the edit is approved and no more changes are made to timing or shots. Online, color, VFX, and the final mix all depend on it, so it is the most important date in the back half of the schedule.
Plan at least two: a first cut to the agency and a cut to the client, each with time for notes and revisions. Add a third round for new clients, complex creative, or heavy legal review. Each round needs a send date, a notes deadline, and revision days.
Yes. Assign post events and tasks to each person, then filter the Workback Master Calendar by person to see everything they're booked on, with their time off underneath. Freelancers can be tracked without a seat.
Yes. Copy the table into a spreadsheet, or rebuild it in Workback during the free 30-day trial and save it as a workspace template for every job after.